The ribbon is cut on the new wing, residents are scheduled to move in on Thursday, and on Wednesday afternoon somebody asks whether the Wi-Fi works in there yet. Too often the answer is "the cables are in," and that is only the beginning of the answer.
An addition does not get its own separate network. It has to join the one you already depend on, with the same charting system, phones and nurse call. How well that connection is planned decides whether go-live day is dull or stressful.
The backbone is the main link between the existing network equipment and the new wing. Everything in the new wing passes through it, so it has to carry far more than a single room's traffic.
For a wing attached to the main building, the backbone is usually fiber optic cable. Fiber is preferred for the run between closets because it carries a lot of data, is not affected by electrical noise, and does not conduct electricity from one area to another. Copper is generally used for the shorter runs from a closet to each room.
Ask your IT provider and contractor how many fiber strands are being installed, because installing extra strands now costs much less than pulling more later. Ask where the fiber will be routed, and whether a second path exists if the first is damaged by a future project.
A wing needs at least one telecommunications closet where cabling from the rooms ends and equipment lives. Closets are often treated as leftover space, and they should not be.
Checklist for the room itself:
Enough space to work, with clear access to the front and back of the rack.
Dedicated electrical circuits, and consider a battery backup unit so the wing survives a short power blip.
Cooling and ventilation that keep the room from heating up, since equipment gives off heat.
A lock, and a log of who has the key.
Not shared with water heaters, laundry or storage, and not under a pipe that can leak.
If the new wing will have several closets, plan the layout so no cable run to a jack is longer than the cabling standard permits. Your cabling contractor can confirm the distance limits.
The new wing needs switches that provide enough ports and power for the devices planned, such as access points, phones, cameras and nurse call stations. Some devices draw their power through the network cable, so the switch must have enough power capacity for all of them. Ask your provider to total it up instead of guessing.
Leave spare ports and spare capacity. A wing that fills every port on day one needs new equipment when the first new device arrives.
Plan wireless coverage at the same time. A wing with thick walls and a long hall behaves differently than the older building, so it needs its own design and a survey after the walls are up, not a guess that mirrors the old wing.
Cutover day is when the wing goes live on the network. Settle these ahead of time:
Which network segments the new wing will use, so devices there are separated sensibly from guest Wi-Fi and from each other.
The addressing plan, so new devices do not collide with existing ones.
Which systems must work on the first day, such as nurse call, charting, phones and door access, and who confirms each works.
A written test list, one line per room type, that someone physically checks.
A way back, if something fails, that does not leave the existing wing affected.
Do the link-up in the morning, not at the end of a shift. Have your IT provider, the contractor's technician and a representative from your nurse call and phone vendors available, or at least reachable. Test with real equipment: a charting workstation, a mobile cart, a wireless phone and a call light, in more than one room.
Then check the existing building. A new link can occasionally disturb what was working, so ask nursing to confirm normal operation on the old halls before the crew leaves.
Keep a paper downtime procedure available for the first few days. Walk the wing again after the first full shift, when real use finds the problems tests missed.
Before the project is closed out, get updated drawings, port and cable labeling, certification results, configuration backups for the new equipment, and a record of the fiber routing. Add the new equipment to whatever monitoring and replacement plans you keep for the rest of the building.
UnityCare IT designs and supports the network side of additions, including the backbone, closet layout, equipment sizing and wireless design, and we can be on-site for cutover day. We work with your contractor and your other vendors so the wing joins the existing network without disrupting residents or staff.
Wi-Fi, switching, firewalls and internet that hold up across a whole facility.
Call or text: 405-285-3845
New customers: start@unitycareit.com
Existing customers: support@unitycareit.com
Service area: based in Edmond, Oklahoma, serving Oklahoma, Texas and Kansas
Hours: Mon–Fri 8 AM–5 PM CT; 24/7 after-hours support